> Got a call, yesterday. Company wants me to estimate
> for changing filters on HVAC units at stores. They want
> a list of prices, based on the tonnage of the unit.
>
> I *went to the one store they needed estimate. Found
> several specific conditions and factors that would change
> the ammount of labor and bother needed.
>
> The furnace was 12 feet above the floor. In a cage, with
> one door. By the bottom of the doorway was a gas pipe
> and a PVC drain, making it unsafe to put an extension
> ladder. Also, the warehouse is tightly packed, making
> it dificult to get an extension ladder to where it's needed.
>
> And, they want me to quote all "# of tons" units the same.
>
> Christopher A. Young
> Learn more about Jesus
> *www.lds.org
> .
Just give them one lump sum price for everything otherwise theyll try
and get you to just do a few of them that are virtually unreachable
and theyll do the rest. Tell them its the only way you quote it.
Walk from it if they give you a hard time. Some jobs are not worth it
and especially if your safety is exasterbated from dangerous working
conditions.